Woodstock WWTP Biogas Utilization Project
Status: Review
Purpose
Oxford County is undertaking a biogas utilization upgrade at the Woodstock Wastewater Treatment Plant (WWTP) as part of the County’s 100% Renewable Energy Plan. This project will implement a Combined Heat and Power (CHP) system to generate heat and electricity from biogas produced at the WWTP, thereby decreasing the WWTP’s dependence on the energy grid.
Scope
Pursuant to the Act and Regulation, the facility, in respect of which the project is to be engaged in, is considered to be an Anaerobic Digestion Facility Class 3. If approved, this facility would have a Combined Heat and Power (CHP) system total maximum name plate capacity of 250 kW.
This new CHP system will offset 40% of the grid electricity used at the WWTP, and 39% of the heat energy requirement at WWTP. This project will reduce the annual greenhouse gas emission for heat and electricity at the WWTP by 58%.
The proposed CHP system will be situated within the current footprint of the WWTP, specifically at its northeast corner. The project does not involve any modifications or upgrades to existing digesters or other active components of the WWTP. Instead, the proposed CHP system will exclusively utilize biogas already produced from existing digesters.
The introduction of a CHP system at the Woodstock WWTP is anticipated to yield significant environmental benefits. By harnessing renewable energy sources for electricity production, the project aims to mitigate the facility’s carbon footprint, alleviating pressure on the energy grid and consequently reducing greenhouse gas emissions from conventional power generation facilities. Moreover, the facility’s emphasis on utilizing biogas for heat generation, rather than relying on natural gas combustion, further enhances its sustainability efforts and contributes to the reduction of its overall carbon footprint.
Public consultation
Public, Indigenous communities, and agency consultation are key components of the renewable energy approval process, and input will be sought throughout the project implementation.
The first hybrid public meeting was held on October 29, 2024, to share information about the project. Watch the video recording | Read the public notice
The second hybrid public meeting was held on February 25, 2025, to share information about the project. Watch the video recording | Read the public notice
Study documents
- Notice of ERO Posting - Woodstock Wastewater Treatment Plant Biogas Utilization Project (Jan 29, 2026)
- Notice of Public Meeting #2 - Woodstock Wastewater Treatment Plant Biogas Utilization Project (Feb 2, 2025)
- Notice of Proposal and Public Meeting - Woodstock Wastewater Treatment Plant Biogas Utilization Project (Oct 29, 2024)
- Project Description Report PDR - WD-WWTP_BUP v4 (Jan 21, 2026)
- Project Description Report - WD-WWTP_BUP (Oct 8, 2025)
- Project Description Report - WD-WWTP_BUP (April 8, 2025)
- Project Summary Report - WD-WWTP_BUP (Dec 13, 2024)
- Design and Operations Report - WD-WWTP_BUP (Jan 26, 2026)
- Design and Operations Report - WD-WWTP_BUP (Draft) (Nov 25, 2024)
- Odour Study Report WD-WWTP_BUP (Jan 23, 2026)
- Odour Study Report WD WWTP BUP (July 19, 2024)
- Emission Summary and Dispersion Modelling Report - WD-WWTP_BUP (Jan 23, 2026)
- Emission Summary and Dispersion Modelling Report - WD-WWTP (Aug 19, 2024)
- Construction Plan Report - WD-WWTP_BUP (Jan 21, 2026)
- Construction Plan Report - WD-WWTP_BUP (draft) (Nov 22, 2024)
- Hydrogeological - WD-WWTP_BUP R1 (Jan 21, 2026)
- Hydrogeological - WD-WWTP_BUP (Draft) (Nov 22, 2024)
- Cultural Heritage Assessment - WD-WWTP_BUP (Nov 4, 2025)
- Municipal Consultation Form - Oxford County (Oct 2025)
- Municipal Consultation Form - City of Woodstock (Oct 2025)
- Natural Heritage Assessment WD-WWTP_BUP (Updated Oct 1, 2025)
- Water Assessment Report - WD-WWTP_BUP (Updated Sept 15, 2025)
- Min Environment Conservation Parks - Screening Comments (Aug 15, 2025)
- Decommissioning Plan Report - WD-WWTP_BUP (March 25, 2025)
- Water Assessment Report - WD-WWTP_BUP (March 25, 2025)
- Surface Water Assessment Report - WD-WWTP_BUP (March 25, 2025)
- Stormwater Management Plan - WD-WWTP_BUP (March 25, 2025)
- Effluent Management Plan - WD-WWTP_BUP (March 25, 2025)
- Traffic Management Plan- WD-WWTP_BUP (March 25, 2025)
- Acoustic Assessment Report - WD-WWTP_BUP (Sept 10, 2024)
- Stage 1 Archaeological Assessment Report - WD-WWTP_BUP (June 3, 2024)
- Natural Heritage Assessment - Species at Risk Memo - WD-WWTP_BUP (March 19, 2024)
- Natural Heritage Assessment WD-WWTP_BUP (Dec 12, 2023)
Project contacts
Nathan Gerber
Coordinator, Energy Management
Oxford County
519-539-9800 ext. 3240 | Email contact
Sean Speer
Senior Environmental Engineer
J.L. Richards & Associates (JLR)
226-770-5120 | Email contact
Kerry Tuyen
Director of Innovation, Technology and Alternate Delivery
Ontario Clean Water Agency (OCWA)
905-301-1957 | Email contact