Second public information meeting for Oxford Road 9 (Hamilton Rd/King St) reconstruction in Ingersoll
A Public information meeting will be held on Tuesday, October 28 for residents to learn project details and speak to Public Works staff about upcoming construction
Oxford County is beginning infrastructure improvements on Oxford Road 9 (Hamilton Road / King Street) from CPKC Railway west to the Town of Ingersoll boundary and the intersection of Oxford Roads 9 and 10 (Ingersoll Street South).
This work will include relocating utilities; installing sanitary sewer, watermain, curb and gutter; new traffic signals at Oxford Roads 9 and 10 and new street lighting; storm sewer improvements; sidewalk upgrades; and landscaping and restoration.
Construction will be carried out in two phases:
- November – December 2025: Start of sanitary sewer preparations
- January – December 2026: Sanitary sewer, watermain and storm sewer, full road reconstruction, traffic signals, and final surface (asphalt) treatments
Please note construction schedules are weather dependent and subject to change based on contractor availability and other factors.
Members of the public who would like to learn more about the project are invited to attend the second Public Information Centre where they can hear project details and speak to Public Works Engineering staff.
Tuesday, October 28, 2025
Drop-in from 4:00 – 6:00 p.m.
Ingersoll Town Hall – Council Chamber
130 Oxford Street, 2nd Floor
During Phase 1 of construction, Oxford Road 9 will be closed to through traffic. Traffic will be
limited to local residents, businesses and emergency services. There will be a planned detour route in place and detour signage posted for the duration of the road closure.
Detour: Oxford Road 45, Road 60 and Oxford Road 10 (Ingersoll Street North)
Information about Phase 2 will be shared closer to the construction start date.
Please note that additional local detours routes may be in place at set periods during construction.
While Oxford County makes every effort to complete projects as efficiently as possible, construction timelines are estimates only and depend on weather, contractor availability and other factors.